With a further 760 meters added to the existing sealed taxiway and a width of 10.5 meters, the taxiway is near completion. Surplus millings were used from the runway overlay to construct the taxiway. The new taxiway will aid the flow of air tr
News
-
Tuesday, February 14, 2012
-
Wednesday, November 16, 2011
Taupo Airport has taken out the prestigious Regional Airport of the Year Award at the NZ Airports Association's annual conference, highlighting a successful few years for the Taupo Airport including some major redevelopments and a more commercially orientated direction.
-
Thursday, August 18, 2011
Works is now complete on the terminal car park with an additional sealed area, previously grass, providing a much need area for public parking.
-
Wednesday, March 16, 2011
The runway works was completed in February, with an extra 25mm thickness, increasing the pavement strength. With the centre line raised, ensuring water run off we can expect a greater longevity and durability from the runway.